Wednesday, April 7, 2010
"Buying a Share" of Prescott Pines
Thursday, March 18, 2010
Repairs Are Starting to Progress
On Wednesday, we were finally able to start coating the inside of the Waste Water Treatment tank. We were unable to do this during the snow, because the special paint that we use must have five days of warm and dry weather in order to cure properly. Once the paint dries, we will be able to reconnect the system.
This week a group of volunteers from the SOWERS project tore down and hauled away the debris from Hilltop #2. The debris needed to be removed so that the county officials can come and inspect the foundation and make sure that it was not damaged by the fire, before we start the rebuilding process. We are starting to work on building plans for this new lodge, and hope that this will be the prototype for future lodges here at camp.
- Please pray that their are no more rain or snow showers in the next week, so we can finish the work needed on the Waste Water Treatment Plant.
- Please pray for the permitting and inspection process both for the Dining Hall and Hilltop #2. Pray that the paperwork would go through quickly so the rebuilding can begin.
- Please pray as we raise funds for the Dining Hall repairs and renovations that God would provide all we need.
Jim
Wednesday, March 3, 2010
One Repair Down...
Last week we had a crew dig out the excess dirt and mud from the hole where the tank belongs. There was so much material to move, they had to use a Bobcat tractor down in the pit, to get everything removed.
The crane came back on Monday to lower the tank back into the ground.
While we had the tank out of the ground, we used the opportunity to reinforce some welds and to repaint the outside of the tank to prevent rusting. We also installed a drain system so that the will not happen again (hopefully)!
Thank you for your continued support and prayers as we move forward with all the repairs.
Jim
Friday, February 19, 2010
Waste Water Treatment Plant Repairs - Update
Well, we have been dealing with delays caused by the weather, so there has been little new news to share, until today.
For the past few weeks we have been having scattered snow showers, and the mud and slush from the snow melt has kept us from bringing a crane down from Flagstaff to lift the waste water treatment plant out of the ground for repairs. Thanks to the beautiful sunny weather we finally had in the last week, by Wednesday of this week, the ground was dry enough for the crane to lift the 41,000 pound tank out of the hole. We are now in the process of digging out all the mud and dirt that was displaced with the flooding, so we can reset the tank in the ground. In addition, while the tank is out of the ground, we will have the chance to sandblast and repaint it with the needed coating, the next step in the continued renovation of the plant to bring it up to current code.
Please pray that the rain this weekend does not stop us from resetting the tank next week! Too much mud means we will have to delay the process.
Jim
Friday, February 5, 2010
Meet The Newest Member of Our Team
When I started I was so stressed about messing things up. I was not only the newest person on the staff, but I had also never worked for Prescott Pines before. However, what I’ve found during my time so far is that the camp office is such a relaxed atmosphere and so encouraging that it’s really easy to get done what needs to be done. I’ve only been here for a few weeks but I’ve already learned so much about the camp and the people that work here. I’d say it was the perfect fit for what I need. I’m really glad to be able to help the camp in the coming weeks and excited to see what else I will learn from this experience.
Tuesday, January 26, 2010
Waste Water Treatment Facility Damage Update
From that point, we plan to raise the main treatment plant using a crane, dig out the dirt that displaced the tank during the flooding, and reposition and repair the facility. As we pass from winter into spring, it will be our priority to reset this system before our number of guests picks up from spring into summer. At this point, we are still unsure of the costs that this repair will involve, however, it has been confirmed that it will not be covered by our insurance.
We are anticipating holding our Winter X camp this weekend as long as the weather holds and the temporary instillation can be completed.
Please continue to pray as we make crucial decisions over the next few days and weeks. Please pray that God will provide the funding needed for these repairs. God is good and we know He has a purpose for all of this, we are just waiting to see what it is!
The treatment plant should be level and the rim below the railing should be 4" above the ground
This picture is looking up to the camp. The water from the camp came down the hillside and caused the flooding that lifted the tank out of the ground like a ship!
This is looking toward the grass field. The pipes going in and out of the tanks are all broken.
Friday, January 22, 2010
More Storm Damage - Please Pray
Please Pray
- That the power would be restored soon.
- That the new storms predicted for the next several days, will cause no further damage.
- That the camp staff and leadership would have wisdom in deciding what direction to take next.
Thank you for your faithful prayers. We will keep you updated as we know more.
